MODERNIZATION AND LIFETIME EXTENSION OF UNIT 2 OF THE ARMENIAN NPP

Project Description

The Armenian Nuclear Power Plant (ANPP) is the only nuclear power plant in the South Caucasus, generating more than one-third of all electricity produced in Armenia. The commissioning of the Armenian NPP in 1980 covered 40% of the electricity balance in the entire Armenian market. Projects for the modernization and lifetime extension of Unit 2 of the Armenian NPP, as well as service maintenance of the plant, are key within the framework of Russian-Armenian cooperation in the energy sector and pursue the following objectives:
Restoration of operational capability
Extension of service life
Enhancement of safety and efficiency levels

10 Years in Armenia

01
Lifetime extension until 2026 and modernization of the Armenian NPP
02
Service for the NPP
  • - repairs
  • - modernization of systems and equipment
  • - supply of spare parts and equipment
  • - engineering and technical support for operation
03
Second lifetime extension of the Armenian NPP until 2036

Lifetime Extension until 2026 and Modernization of the Armenian NPP (2015-2021)

As part of the modernization and lifetime extension of the Armenian NPP until 2026, JSC "Rosatom Service" acted as the general contractor for the scope of work. Extensive work was carried out with the involvement of specialized Russian organizations and institutes:
Repair of steam generators
Modernization of the ECCS
Installation and removal of condensers
Replacement of steam superheater moisture separators
Modernization of turbines and replacement of turbogenerators
Replacement of unit transformers

General Project Description

Overall, as part of the turbine equipment modernization, 1,500 tons of new main equipment were supplied to the turbine hall, including 2 turbines, 4 condensers, 2 turbogenerators, 2 unit transformers, 4 steam superheater moisture separators, and 6 ECPs.

Work on the reactor plant included modernization of safety systems and automated control systems, as well as justification for the further operation of the reactor plant and about 5,000 pieces of equipment, including:

  • - A complex of R&D: inspection, calculations (thermal-hydraulics, strength, etc.), metallurgical studies, non-destructive metal testing
  • - Repair of the reactor plant (vessel, upper unit, SG)

In 2021, as part of the plant's modernization and lifetime extension until 2026, a unique reactor vessel annealing operation was also carried out. The reactor vessel is the main non-replaceable component of a nuclear power plant. The annealing process restored the performance properties of the reactor's metal shell to 80-85% of their original condition and extended the service life of the reactor vessel until 2039.

As a result of the work performed, the unit's capacity was increased from 380-390 MW to 440 MW.

In 2021, based on the prepared documents, the Armenian regulatory authority made a decision to extend the unit's operating license and issued a license allowing Armenian specialists to operate the nuclear power plant until 2026.

Key Project Figures

800
personnel on site during peak periods
by 10-12%
Electricity generation increased
50+
contractors
1500+
tons of equipment supplied to the ANPP
to 440 MW
Unit capacity increased
At this stage, we have completed a very important procedure for modernizing the plant. This was made possible only through the coordinated work of Armenian and Russian nuclear specialists. And we hope that the result of our joint efforts will further enhance the safety of the NPP and extend its operation until 2026, with a prospect for another 10 years.
Evgeny Salkov
General Director of JSC "Rosatom Service"

Contribution to Sustainable Development

> 2 million
people provided with electricity
1600
jobs preserved for the plant's operational personnel
14 km
of supplied railway tracks
Thanks to the implementation of a whole range of measures, Unit 2 of the Armenian NPP meets the most modern international requirements. The operation of the Armenian NPP has been extended until 2026. This large-scale project can, without exaggeration, be called one of the most important in Armenia, and today, in this anniversary year, our Armenian NPP has been given a second life.
Eduard Martirosyan
General Director of "Haykakan Atomayin Elek'trakayan" CJSC

Second Lifetime Extension of the Armenian NPP until 2036

On December 15, 2023, JSC "Rosatom Service" and "Haykakan Atomayin Elek'trakayan" CJSC signed an agreement on extending the operating life of the Armenian NPP until 2036. The agreement on the second lifetime extension of the plant was reached during a regular intergovernmental commission on economic cooperation between the Russian Federation and the Republic of Armenia. To obtain a new license for further operation of the NPP from the Armenian Nuclear Regulatory Safety Committee, a number of measures must be carried out between 2023 and 2026, including inspection, potential repair, and modernization of equipment. Work on the second lifetime extension of the plant is currently underway.

Completion of the Annual Work Scope within the Framework of the Second Lifetime Extension at Unit 2 of the Armenian NPP

In 2025, a significant set of measures was completed, aimed at further enhancing the safety and reliability of the only nuclear power plant in the Republic of Armenia, as well as confirming the possibility of operation during the repeated additional term.

Key Results of 2025:

Safety Assessment and Assurance:


  • The full set of initial data has been collected and an analysis of fire impact on the safe shutdown of the reactor plant has been initiated to assess the sufficiency of fire protection.

  • The technical condition and residual life of a number of building structures, buildings, and facilities have been determined, including the spent fuel pools of Units 1 and 2, the emergency boron injection unit, solid low-level waste storage facilities, as well as electrical equipment and cables of safety-related systems within the responsibility of the Russian side according to the contract division.

  • Work has begun to determine a new configuration of the Emergency Core Cooling System (ECCS) to expand the spectrum of considered design basis accidents.

  • Power Plant personnel have been certified in destructive and non-destructive testing methods.

Equipment Modernization and Inspection:


  • Modernization of ventilation and air conditioning systems for the boron injection unit (V&K BU) and the planned 2025 volume for the Essential Service Water System (ESWS) has been completed, including the assembly of prefabricated piping modules with quality control.

  • Secondary instrumentation and primary transducers for the control and automation panels have been supplied; new emergency lighting panels have been delivered.

Scientific and Technical Justification for Lifetime Extension:


  • The specimen assemblies with witness samples were removed from the reactor vessel and delivered to a research institute for analysis of the metal properties. The results will serve as the foundation for evaluating the reactor vessel condition.

  • A set of documentation on reassigning the service life of reactor plant equipment and pipelines until 2031 has been developed and handed over to the customer, including radiation load calculations, thermal-hydraulic calculations, and boundary condition calculations.

  • Methodologies for assessing reactor plant equipment and pipelines, Main Circulation Pumps (MCPs), and main isolating valves have been developed and agreed upon. The preliminary assessment of the aforementioned NPP elements confirms the presence of residual life in key equipment.

Preparatory and Design Work:


  • Expert review and supervision of neutron-physics calculations for the 37th fuel loading of the VVER-440 reactor have been conducted.

  • Design documentation for the modernization of MCP oil supply systems has been developed and submitted for approval.

The coordinated teamwork of Russian and Armenian specialists ensured the planned completion of all activities scheduled for 2025. Steady progress in implementing the PLE-2 project lays a solid foundation for the safe and reliable operation of Unit 2 of the Armenian NPP during the extended operational period.

Considering Rosatom's unique experience in extending the operating life of the Kola and Novovoronezh NPPs, as well as taking into account the positive results of the first stage of modernization of the Armenian NPP, partnership with the State Corporation under the concluded agreement will allow the plant to operate efficiently and safely until 2036.
Yuri Sviridenko
in 2025 - Director for Complex Project Management